‘Walking Safe’ Project Update

The Walking Safe Cayuga Heights Sidewalk Project

The Scope of Work for this project is to construct a new concrete sidewalk (with associated grading and drainage), from the top of Kline Road (at Highland Road) down to Wyckoff Road and then down to the east side of Cayuga Heights Road. Bothar Construction has been hired to do the work as engineered by Fisher Associates. Upon completion of the work within the contract, the Village DPW will begin the work to complete the sidewalk along Wyckoff Road down to the Lakeview Cemetery Entrance.

The project is schedule to begin on April 15, 2024 and should be completed within 8-10 weeks (see Bothar Schedule below). The Village DPW will not begin work on the lower sections until some time after June 1, 2024.

Bothar Construction’s Schedule of work is as follows (starting April 15, 2024):

  • Mobilization, Road Closure with Detour Installation- April 15th
  • Saw Cutting of Roadway for excavation- estimated 2 days to complete
  • Drainage Installation with pipe- Estimated 3 weeks to complete
  • Excavation and grading including subbase for new curb and sidewalk- Estimated 2 weeks to complete after drainage
  • Forming and pouring of sidewalk and curbing- estimated 2 weeks to complete
  • Restoration work: Asphalt, grading, topsoil, seed and mulch- 1 week to complete after sidewalk install
  • New signs and Striping- 3 days of work after all other work is completed.

The intent is to close the street to through traffic for the duration of the construction work.

Residents will always be allowed to drive through the construction zone to reach their homes.

Occasionally, you may need to approach your house from the opposite end of the street.

When the time comes for concrete to be poured, Bothar will provide a temporary bridge across the new sidewalk for your driveway and front door access.

Bothar will provide access for the mailman to drive through the site and also provide a temporary mailbox standard until ready for the final installation.

Working hours will be 7am to 5pm daily, but not on weekends.

The following is a list of key participants that you may contact in the event there is a question that needs to be addressed:

Brent Cross, Village of Cayuga Heights Superintendent of Public Works, phone: 607-257-5536, email: bcross@cayuga-heights.ny.us

Michael Wiese, Director of Public Works Operations, phone: 607-591-7939, email: mwiese@cayuga-heights.ny.us

Pete Wlodarzyck, Fisher Associates Project Engineer, phone: 585-749-0703

Brent Rauber, Fisher Associates Construction Manager, phone: 607-382-0996

Fisher Associates Construction Inspector TBD

David Leach, Bothar Construction, phone: 607-242-4435

Recent Posts

Arbor Day Celebration

In 2023, Cayuga Heights achieved Tree City certification by the Arbor Day Foundation for the 11th consecutive year.  Tree City certification recognizes a municipality’s commitment to maintain and increase its trees

Read More »

Construction has begun!

Finally, after a long six years of planning, work has begun on the ‘walking safe’ sidewalk project! This means that from the top of Kline Road (at Highland Road) down

Read More »

‘Walking Safe’ Project Update

The Walking Safe Cayuga Heights Sidewalk Project The Scope of Work for this project is to construct a new concrete sidewalk (with associated grading and drainage), from the top of

Read More »
Skip to content